James Bay Niobium PEA Delivers an After-Tax NPV(8%) of $1.0 Billion and IRR of 27.5%

Press Release

Montreal – Niobay Metals Inc. (“NioBay” or the “Company”) (TSX-V: NBY) is pleased to announce results of an independent Preliminary Economic Assessment (the “PEA’’) for its wholly- owned James Bay Niobium project (the “Project”), located 40 km south of the island of Moose Factory, Northern Ontario. The PEA was prepared with independent engineering firm G Mining Services Inc. (“G Mining”).

A conference call will be held on Wednesday, October 14th at 16:00 EST. Dial-in information can be found below.

Because of the geometry and location of the deposit, three mining scenarios were evaluated i.e. open pit (scenario #1), underground (scenario #3) and a hybrid of both mining methods (scenario #2). Details of the financial and technical highlights of all three scenarios are available on the NioBay website at http://niobaymetals.com/wp/en/home-2/

Table 1: PEA Highlights (all figures in CAD$ unless otherwise noted)

Open Pit Open Pit + UG Underground
Pre-Tax Internal Rate of Return (IRR) 33.6% 33.4% 26.0%
Pre-Tax Net Present Value (NPV) 8% $1,475 M $1,268 M $1,104 M
Pre-Tax Payback (years) 2.6 years 2.5 years 3.8 years
After-Tax Internal Rate of Return (IRR) 27.5% 27.0% 21.6%
After-Tax Net Present Value (NPV) 8% $1,008 M $856 M $733 M
After-Tax Payback (years) 3.2 years 3.1 years 4.3 years
Pre-Production CAPEX (incl 25% Contingency) $510.5 M $482.0 M $579 M
Average Annual LOM Niobium Production 5,470 t Nb 6,213 t Nb 6,283 t Nb
Mine Life 30 years 23 years 23 years
Total Mineral Resources Mined 70.8 Mt 53.7 Mt 53.6 Mt
Average Grade Mined 0.44 % Nb2O5 0.51 % Nb2O5 0.51 % Nb2O5
Gross Revenue After Royalties (LOM) $9,264 M $8,360 $8,454
After-tax Operating Cash Flow (LOM) $3,581 M $2,696 M $2,536 M
 

C1 Costs over LOM*

US$16.10 / kg

Nb

US$18.45 / kg

Nb

US$19.11 / kg

Nb

$48.48/t $63.85/t $66.94
 

All-in Costs (sustaining CAPEX + Closure + OPEX)

US$17.58/kg

Nb

US$20.52 / kg

Nb

US$21.43 / kg

Nb

$52.93 / t $70.98 / t $75.08 / t
LOM Niobium Price US$45/kg Nb US$45/kg Nb US$45/kg Nb
Exchange Rate (CAD/USD) 1.30 1.30 1.30

*C1 Cost is mine site, transport, marketing and royalty

Claude Dufresne, President & CEO, commented: We are very pleased to finally be able to demonstrate the value of the James Bay Project as highlighted with the PEA. All three scenarios deliver robust returns but also provide strong and long-term economic opportunities to shareholders and to local stakeholders.”

Claude Dufresne continued: “We are excited to move to the next phase that will include a definition drilling program, baseline and technical studies, and strengthen our engagement and business relationship with Moose Cree First Nation and other stakeholders.”

Conference Call Details
Participant Toll Free Dial-in Number: +1(833) 900-1546
Participant International Dial-in Number: +1(236) 712-2464

An operator will direct participants to the call.

The conference call replay will be available from 1:00 p.m. (Eastern time) on October 14, 2020 until 11:59 p.m. (Eastern time) on October 21, 2020 with the following dial in numbers: 1-(800) 585-8367 (North American toll free) or 1-(416) 621-4642, access code 9182784. The replay will also be available on our website at www.niobaymetals.com.

Table 2: Capital Costs

Capital Costs by Area (in CAD$M) Open Pit OP + UG Underground
Infrastructure 133,575 133,575 112,615
Power & Electrical 31,485 31,485 31,485
Water & Tailings 31,413 13,575 20,482
Mining U/G 117,729
Mining Pre-production 31,312 31,338
Mining Equipment OP 29,405 29,405
Process Plant 69,985 69,985 99,985
Other Equipment 5,613 5,614 5,612
Total Direct 332,788 314,977 387,908
Construction Indirect 35,018 32,699 34,772
General Services 40,406 37,730 40,122
Pre-Prod, Startup, Commission 150 150 150
Contingency 102,090 96,389 115,738
Total Indirect 177,664 166,968 190,782
Total CAPEX 510,452 481,945 578,691
Sustaining Costs 283,163 359,123 416,080
Closure Costs 32,418 23,992 20,692

Table 3: Operating Costs

Operating Costs by Area ($/t) Open Pit OP + UG Underground
Mining Costs* 12.13 26.42 29.44
Processing Costs 14.60 14.62 14.62
Converter Costs 11.48 12.76 12.89
G&A 10.00 10.00 10.00
Total 48.48 63.85 66.94
US$/ kg Nb 16.10 18.45 19.11

*Unit mining cost of $4.43/t based on 1.8 strip ratio and including stockpile rehandle.