NEB releases preliminary timeline for Energy East

Press Release

April 26, 2016 – Calgary, Alberta – National Energy Board

The National Energy Board (NEB) has released a preliminary timeline for the Energy East hearing process.

This timeframe reflects an extended time limit of 21 months for the process, as directed by the Minister of Natural Resources. National Energy Board reviews are typically conducted within a 15-month time limit.

The following table outlines the expected steps and timing that the NEB plans on following to consider the amended Energy East project application. This information is subject to change. The NEB will provide further details as they become available.

Expected Process Step Expected Timing
Filing of Consolidated Application by Energy East Pipeline Ltd. Mid-May 2016
Issuance of List of Participants Early June 2016
Issuance of Hearing Order (including completeness determination) Mid-June 2016
Panel Sessions in communities along pipeline route August – December 2016
Written Process for Participants January – May 2017
Draft Conditions for Comment Mid 2017
Final Argument November – December 2017
NEB Report to Governor in Council March 2018

The NEB expects to gather input from the hearing participants on what process elements they would like to see included in the review. The NEB will use this feedback to help design a process that is thorough, rigorous and transparent.

Quick Facts

  • Energy East is a 4,500-kilometre pipeline proposed to carry 1.1-million barrels of crude oil per day from Alberta and Saskatchewan to refineries in Eastern Canada and a marine terminal in New Brunswick.
  • In December 2015, Energy East Pipeline Ltd. filed project amendments to remove the Cacouna marine and tank terminal, change the pipeline route and facility locations in Quebec, modify the tank storage facility in New Brunswick, and to address the agreement reached with three local distribution companies in Eastern Canada.
  • The NEB has received more than 2,300 applications to participate in the Energy East hearing process.

Associated Links

  • 26 April 2016 National Energy Board Letter to TransCanada
  • 22 April 2016 National Energy Board Letter to the Energy East and Eastern Mainline Panel
  • Energy East Project NEB page

The National Energy Board is an independent federal regulator of several parts of Canada’s energy industry with the safety of Canadians and protection of the environment as its top priority. Its purpose is to regulate pipelines, energy development and trade in the Canadian public interest. For more information on the NEB and its mandate, please visit www.neb-one.gc.ca.

– 30 –

Contacts

Sarah Kiley
Communications Officer
Sarah.Kiley@neb-one.gc.ca
403-299-3302
1-800-899-1265

Marc Drolet
Agent de communications
Marc.Drolet@neb-one.gc.ca
514-476-9911
514-283-2261

ILR5

NationTalk Partners & Sponsors Learn More