Press Release
March 23, 2016
Stornoway Diamond Corporation (TSX-SWY; the “Corporation” or “Stornoway”) announced today its results for the truncated quarter and fiscal year ended December 31, 2015. These results are pursuant to Stornoway’s recent change in year end from April 30 to December 31, undertaken to better align the Corporation’s financial, operational and regulatory reporting ahead of first production at the Renard Diamond Project.
Quarter ended December 31, 2015 and FY2015 Highlights
(All quoted figures as at December 31, 2015 and in CAD$)
Subsequent to December 31, 2015, the project’s construction schedule was re-baselined with first ore delivery to the Renard diamond process now expected by the end of September 2016 and commercial production (60% of plant capacity achieved over 30 days) expected by December 31, 2016. This represents a five month improvement on the previous schedule, which assumed commercial production in the second calendar quarter of 2017. The re-baselined schedule resulted in a commensurate reduction in the forecast cost to complete, from $811 million to $775 million.
Matt Manson, President and CEO, commented “Construction progress at Renard continued to track ahead of schedule during the last two months of our truncated FY2015, which gave us the confidence to re-baseline our schedule and cost to complete forecasts for future progress reporting. At the end of February construction progress stood at 74.1% compared to the new plan of 72.4%, as our construction team continued to out-perform expectations. An updated mine plan for the project, based on the results of the updated 2015 Mineral Resource and revised construction schedule, will be released shortly. With the diamond market beginning to recover after a challenging 12 months, we look forward to achieving first diamond production at Renard later this year based on a foundation of solid project execution and with a stronger than expected balance sheet.”
ILR3