Press Release
Toronto, Ontario–(Newsfile Corp. – July 21, 2020) – IAMGOLD Corporation (TSX: IMG) (NYSE: IAG) (“IAMGOLD” or the “Company”), together with joint venture (“JV”) partner Sumitomo Metal Mining Co., Ltd. (“SMM”), is pleased to announce the decision to proceed with the construction of the Côté Gold Project (“Côté”, or the “Project”). The Project, located in northern Ontario approximately 20 km southwest of Gogama, 130 km southwest of Timmins, and 200 km northwest of Sudbury, is a 70/30 JV with SMM.
The decision enables construction start in Q3 2020 with activities ramping up into Q4 2020. Côté construction will incorporate protocols to ensure the health and safety of employees, contractors and host communities in respect of COVID-19.
Gordon Stothart, President and CEO of IAMGOLD, commented, “The Côté Gold Project is transformational to the future of IAMGOLD. At a gold price of $1,700, Côté’s expected NPV (on a 100% basis) is over $2 billion, with a 22.4% IRR. The Project is anticipated to generate over 1,000 jobs during construction, 450 jobs during operations, C$5 billion in wages and more than C$10 billion in GDP over its lifespan. Côté is a world-class deposit located in Canada, with estimated contained gold reserves of over 7 million ounces and exploration potential. Today’s construction decision for the Project positions the Company well for the future by reducing overall operating costs (per ounce of gold), increasing total production capacity, increasing the number of operating mines and creating greater balance in our geographic diversity. While we focus on building Côté, we will continue to apply our de-risking approach to the Boto Gold Project in Senegal, commencing with meaningful investment in local infrastructure. We are very excited about building our growth pipeline and the future of the Company. We look forward to providing you with updates on our progress.”
Capital Spend and Financing:
IAMGOLD’s expected go-forward capital obligation (exclusive of sunk costs) is $875 – $925 million for its 70% share of project construction costs, assuming the leasing of major mining equipment of approximately $80 million. This capital is expected to be expended over the following time period, assuming a go-forward U.S. $ / Canadian $ exchange rate of 1.35:
The above spend is anticipated to be financed through cash flows from IAMGOLD’s operations and its balance sheet, which stands at over $800 million in cash, cash equivalents and short term investments as at March 31, 2020. In addition, the Company currently carries a virtually undrawn committed credit facility of $500 million, the majority of which matures in 2024.
To mitigate financial exposures associated with the expenditures, including currency and commodity risk, and to protect future operating cash flows, the Company may opportunistically enter into derivative contracts. The Company has substantially completed a fuel hedge program over the construction period and has initiated a Canadian dollar hedge program for up to 90% of its Canadian dollar exposure. To date, the Company has hedged just over 5% of the attributable C$ exposure at rates that average $1.3605.
Stakeholder Engagement
The Company has been actively advancing stakeholder engagement as follows:
Engineering, Procurement, Construction Management (“EPCM”)
As noted above, today’s decision enables a construction start at Côté in Q3 2020 with preparatory work to be completed over the summer and activities ramping up into Q4 2020. The preparatory work is anticipated to include fish salvage, construction camp preparation and road access development.
The Project team has completed over 60% of detailed engineering, which has enabled the Company to obtain firm bids and secure prices on all major equipment. To date, 55% of the total project cost has firm pricing, further reducing technical and cost risks for the Project.
The anticipated construction schedule is 32 months, with expected key milestone dates noted below:
The table below summarizes expected Project metrics on a 100% basis.
Table 1 – Summary of Project Metrics (100% Basis) 1
| Units | Feasibility Study Extended Case at $1,250/oz gold |
June 2020 Update at $1,350/oz gold | June 2020 Update at $1,700/oz gold | |
| Mining: open pit | Mine Capacity – Mtpa | 70 | 70 | 70 |
| Process: crush, grind, gravity, leach, CIP | Mill Capacity – Mtpa | 13.1 | 13.1 | 13.1 |
| Mill Daily Throughput | tonnes per day | 36,000 | 36,000 | 36,000 |
| LOM Average Annual Gold Production | Ounces | 372,000 | 367,000 | 367,000 |
| LOM Recovered Gold | million ounces | 6.69 | 6.61 | 6.61 |
| LOM Average Recovery Rate | % | 91.8 | 91.8 | 91.8 |
| Mine Life | Years | 18 | 18 | 18 |
| LOM Average Total Cash Costs | $/ounce | $606 | $600 | $663 |
| LOM Average All-in Sustaining Costs (AISC) 2 | $/ounce | $703 | $771 | $835 |
| Average Grade | grams per tonne gold | 0.97 | 0.96 | 0.96 |
| Average LOM Strip Ratio | waste:ore | 2.6:1 | 2.7:1 | 2.7:1 |
| Estimated Capital Expenditures – go forward basis | ||||
| Initial Capital 3,4 | $ million | $1,147 | $1,304 | $1,304 |
| Sustaining Capital 4 | $ million | $589 | $1,071 | $1,071 |
| Investment Metrics | ||||
| Gold Price Assumption | $/ounce | $1,250 | $1,350 | $1,700 |
| After-tax NPV (5%) | $ million | $905 | $1,121 | $2,037 |
| After-tax IRR | % | 15.4 | 15.3 | 22.4 |
| Payback Period | Years | 4.4 | 3.7 | 2.6 |
Notes:
District Potential
The Project hosts estimated reserves totalling 7.3 million ounces of contained gold (on a 100% basis) in proven and probable reserve categories (calculated at $1,200 per ounce gold) and estimated resources (calculated at $1,500 per ounce) totaling 10.2 million ounces in measured and indicated resource categories (including reserves), with a further estimated 3.8 million ounces in inferred resources (see news release dated February 18, 2020). The Company continues to assess the district potential of its over 500 square kilometres land package through regional exploration.
As announced in early 2019 (see news release dated March 26, 2019), the Company has identified a new discovery called the Gosselin Zone, located 1.5 km northeast of the Côté deposit, and is progressing drilling programs to support a maiden resource estimate, which is expected for completion in 2021.
Quality Control Notes
The information in this news release was reviewed and approved by L-B Denoncourt, P. Eng, Project Manager, Côté Gold for IAMGOLD. Mr. Denoncourt is a Qualified Person as defined by National Instrument 43-101.
CONFERENCE CALL
A conference call will be held on July 21, 2020 at 8:00 a.m. (Eastern Time) for a discussion with management regarding the decision to construct the Cote Gold Project. A webcast of the conference call will be available through the Company’s website at www.iamgold.com.
Conference Call Information:
North America Toll-Free: 1-800-319-4610 or International number: 1-604-638-5340
A replay of this conference call will be available for one month following the call by dialing:
North America toll-free: 1-800-319-6413 or International number: 1-604-638-9010, passcode: 4968#.
Please dial in 10 – 15 minutes prior to the scheduled start time as call volumes are heavy. If you are still unable to connect from your primary telephone network after attempting all of the dial-in numbers provided, if available, please retry using an alternate telephone network.
For further information please contact :
Indi Gopinathan, VP, Investor Relations & Corporate Communications, IAMGOLD Corporation
Tel: (416) 360-4743 Mobile: (416) 388-6883
Phil Rabenok, Senior Analyst, Investor Relations, IAMGOLD Corporation
Tel: (416) 933-5783 Mobile: (647) 967-9942
Toll-free: 1-888-464-9999 info@iamgold.com
Please note:
This entire news release may be accessed via fax, e-mail, IAMGOLD’s website at www.iamgold.com and through Newsfile’s website at www.newsfilecorp.com. All material information on IAMGOLD can be found at www.sedar.com or at www.sec.gov.
Si vous désirez obtenir la version française de ce communiqué de presse, veuillez consulter le http://www.iamgold.com/French/accueil/default.aspx.
To view the source version of this press release, please visit https://www.newsfilecorp.com/release/60165
ILR5